Why tenders mix two standards
Estimators often see “AS 4586” and “slip test” in the same paragraph. The first is about classifying new pedestrian surface materials. The second, when it means a visit to a Brisbane site, is usually measurement of a floor that is already there or will be there after install. Treating them as one line item is how an allowance ends up too thin for the visit, or priced for work that a supplier report has already covered.
Start with the words on the page. If the documents ask for a P classification of a nominated tile, that is typically a product classification under AS 4586:2013 — often sitting with the manufacturer or a laboratory report on unused samples. If they ask for on-site slip resistance testing of existing entries, amenities, wet areas or a floor the builder is about to take over, that is the AS 4663:2013 situation. If they want a pendulum test of the new floor before practical completion, that is a later visit and a different program date; see before-handover slip testing.
On-site testing is not a product datasheet
Premrest’s site work is wet pendulum testing of selected pedestrian surfaces under recorded conditions. Once a material is on the slab, grouted, coated or worn by following trades, it is an existing surface. A supplier’s AS 4586 slip rating does not travel automatically onto that floor. Say so in the tender response if the client has asked for both a product rating and a site test — they are two deliverables, and only one of them is a site visit.
If the job is a refurbishment of an operating commercial property, the existing floor may need testing before strip-out as well as after the new finish is down. List those as separate visits. The commercial wet-area slip testing page covers how occupied entries, kitchens and outdoor circulation are scoped when the building stays open.
What to put in the price
A slip testing tender allowance is only as good as the variables you lock down. Include:
- The number of areas or distinct surface types, not just “the wet areas”.
- Whether the brief asks for wet conditions, dry conditions, or both, so the method can be confirmed.
- Access: occupied building, construction site, induction, escort, parking and how long each location can be held.
- After-hours or weekend work, if the program will not release the floor during the day.
- A written report — what it must record, who it is addressed to, and whether the superintendent wants a particular format.
Leave a note where the drawings are silent. A quote that says “three amenities, one entry, wet pendulum, after hours, report” is usable. A quote that says “slip testing as specified” is not, because the specification may be mixing a product rating with a site test.
Quote turnaround
Quotes are prepared promptly on receipt of drawings or a written scope. Send the specification clause, a marked plan or finishes schedule, the number of areas you can see, and the access story. There is no published service-level promise on this page; the time to a figure depends on how complete the pack is and whether the clause needs a conversation before it can be priced.
Call 1300 207 915 if you are mid-tender and need help reading whether the clause is asking for a product classification, an on-site test, or both.
After the job is awarded
Once the floor is down and someone asks for a test before handover, occupancy or practical completion, the brief changes. You are no longer pricing a maybe; you are booking a visit to a specific surface. That path is set out on the before-handover slip testing page. Methods and reporting are explained on the slip resistance testing page. The Brisbane wet-area checklist helps you describe conditions on an exposed or still-active site.
The contact page is the quickest way to send drawings. Use the message field for the clause wording, the area count and any after-hours constraint.